By the first week of June 2019 at Trio 2 apartment, decorative suspended ceilings, gypsum plasters, marbles and ceramics have been fully completed. Aluminiums, balcony glass railings, electrical water boilers and air condition inner units are also installed. Screed conrete works are completed apart from ones which are on the ground floor parking area. Exterior emery works for filler and paintings are due to the mid july along with the installation of all sanitary units. Outer units of air conditions installation will be started by the early july.  Trio 3 apartment's task schedule is right on the way by coming after only a month away from Trio 2 apartment. Trio 1 apartment's task schedule is also going as it is planned, and coming after only a month away from Trio 3 apartment.